| Our Finance Manager / Company Secretary Mr. Evans Mutangama |
![]() |
| The able accountant. |
| Engineer Enock Silwamba, Station Manager (MPS) and me. |
| Mr. Prince Mutengo ~ Senior Electrical Technologist |
![]() |
| Task: Refurbish All Canal Spillways Total # 5 Duration = 3.5 Months |
| 16th September 2011 ~ Spillway # 1 - Steel and Roughening (For Bonding between Old and New Concrete) Detail |
| Form-work (Timber) ~ 30 September 2011 |
| Safety Issues. Floaters at Fore-bay in Case of Trouble |
| Cast Concrete with Form-work Untouched |
| Occupational Health and Safety Issues Addressed. |
| The End Product ~2 October 2011 |
| A sample near the offices. |