Task: Refurbish All Canal Spillways Total # 5 Duration = 3.5 Months |
16th September 2011 ~ Spillway # 1 - Steel and Roughening (For Bonding between Old and New Concrete) Detail |
Form-work (Timber) ~ 30 September 2011 |
Safety Issues. Floaters at Fore-bay in Case of Trouble |
Cast Concrete with Form-work Untouched |
Occupational Health and Safety Issues Addressed. |
The End Product ~2 October 2011 |
A sample near the offices. |